MINERvA Project Review
Main
INjector
ExpeRiment
v-A
DOE CD-1/2/3a Review of the MINERvA Project
December 5, 2006
| Overview | CD-2 Documentation| CD-3a Documentation|Other Documents|
Overview of Charge and Experiment
- MINERvA Overview
(pdf)
- DOE CD-2 and CD-3a Scorecard
(pdf)
- Review Presentations by MINERvA Project Team
- Project Overview
(pdf)
- Scintillators (WBS 1.0) WLS Fibers (WBS 2.0) and Clear Fiber Cables (WBS 4.0) (pdf)
- Phototubes (WBS 6.0) PMT Housing (WBS 5.0) and Electronics and DAQ (WBS 7.0)
(pdf)
- Scintillator Plane Assembly (WBS 3.0) Frames Absorbers and Stand (WBS 8.0) and Module Assembly and Veto Wall (WBS 9.0)
(pdf)
Required CD-2 Documentation
- Detailed Resource Loaded Schedule
- Microsoft Project File
(mpp)
- Gantt Chart
(pdf)
- Critical Path
(pdf)
- Costs Note: unless otherwise
indicated, the costs in this table are unburdened FY06$ base costs
(pdf)
- Milestones
(pdf)
- One-Page Summary
(pdf)
- WBS Dictionary
(pdf)
Detailed Cost Estimate
(pdf)
System Functions and Requirements Document (Conceptual Design Report)
(pdf)
Results of and Responses to Site Preliminary Design Review
- Final Closeout Report from Director's CD-2/3a Review
(pdf)
- Response to Director's CD-2/3a Recommendations
(pdf)
Preliminary Design Drawings
(Web Page)
Project Execution Plan
(pdf)
Start-up Test Plan (see Scorecard)
Hazard Assessment
(pdf)
Risk Management
(pdf)
Acquisition Strategy
(3.2MB pdf with signed signature page) or
(323kB unsigned pdf)
Value Management/Engineering Report
(pdf)
Funding Profile
(pdf)
Required Documentation unique to CD-3a
Other Documents
- Integrated Safety Management Document
(pdf)
- Project Management Plan
(pdf)
- MINERvA Project Team (pdf)
- Technical Design Report
(pdf)
- Configuration Management Document
(pdf)
- Quality Assurance Plan
(pdf)
- Top